27/07/17

Mount Gellibrand Windfarm Progress Update

The Mount Gellibrand Windfarm is situated 20km west of Winchelsea at the foot of the historic Mt Gellibrand. WCJV’s scope at the project includes 44 132 MW wind turbine generator foundations and a total of 28 kilometres of access roads. The turbine footings contain a total of 49 tons of steel reinforcement and 360 cubic metres of concrete, which is batched on site at the mobile batch plant. Currently the joint venture has completed approx. 12 kilometres of road construction and exceeded targets by completing 3 foundation main pours last week alone. Short snapshot progress video below.