21/02/18

Civilex Allen Reservoir Dam Milestones achieved, visit by NEW Civilex BBQ Truck


Civilex always work hard to exceed client expectations, and after recently achieving two major project milestones the Allen Reservoir Project Team are certainly testament to this. Milestones achieved were:
1) Establishing access to the concrete works, and
2) Installing the outlet trench and removing the lower tier dewatering.
Both milestones are critical to the Allen Reservoir Project – their on-time completion mitigates a large portion of the project risk which was associated with groundwater inflow during excavation works. In particular, removal of the lower tier dewatering has rounded out the deepest excavation in what was expected to be the most challenging ground conditions on site.
Civilex are proud both milestones were completed on time, and to the highest safety standard.
After a challenging start, the Project Team welcomed the celebrations, and thoroughly enjoyed the new Civilex BBQ Truck’s inaugural visit! Well done to everyone involved!